1. General Information
Click xpress is a revolutionary new system for fitting laminate floors
without the use of glue or any other major tools. The only materials you
will be needing are a pencil, a measuring rod or tape measure, a whip saw
or a fretsaw and a number of spacer blocks. Click xpress: easy, swift and
efficient for a high quality result.
2. Preparation
Lay out the unpacked panels in the middle of the room and allow them to
acclimatise for 48 hours. Ideal average room temperature is around 22C
and the ideal room air humidity is around 55%. Make sure that the height
between the door frames and the doors on the one hand and the sub-floor on
the other hand is at least 1cm |
| |
3. Installation |
 |
Figure 1: Make sure the sub-floor is clean and perfectly level. Any
bumps in excess of 2mm must be leveled out beforehand. The laminate panels
must be fitted crosswise over the sub-floor
|
 |
Figure 2: Position the panel to be fitted with its tongue face at
an angle against the groove face of the panel already in place. If you are
using a groove in tongue joint, do the exact reverse. Then bring down the
new panel: as you do so, it will automatically click-lock in to the panel
already in position, securely fastening itself.
|
 |
Figure 3: Wood continues to be subject to shrinkage and expansion.
Which is why you will need to provide an 8 to 10mm expansion joint on all
sides. |
 |
Figure 4: You can start out fitting the floor either from a corner
or from the middle of the room. Click xpress allows you to work from
right to left. You are best advised to start out from the location of an
obstacle (door opening, radiator, ). Also, bear in mind that you should
start by first click-locking the short sides before moving on to
click-lock a newly created ensemble of 2 panels into the panel already in
position. |
 |
Figure 5: Then gently tilt up the 2 panels which have been locked
along their short face and push the lengthwise face of the 2nd panel into
the row already in position. Here too, the ensemble will automatically
click-lock into the row already in position. |
 |
Figure 6: As of the 4th row, apply the same method of operation for
the 2nd and 3rd row but position yourself on the laminate flooring which
has already been fitted. |
 |
Figure 7: Make sure you provide a 10mm expansion joint. Bear this
in mind as you saw the lengthwise faces of the final row of panels.
Measure up the final row with a sawn-off panel section. |
 |
Figure 8: In case of 2 doors opposite of each other: position the
first plank as close as possible to the door. Slightly lift the plank and
slide it (or tap it) underneath the door step. |
| |
4. Finishing
As soon as you have finished putting your Click xpress laminate floor in
place, the floor can be walked on with immediate effect and finishing
operations can be started.
5. Refitting
Your Click xpress laminate floor can be taken out and refitted without
limitation. Just lift the panels out at an angle, remove and refit them in
the exact same way in the same or a different room, without any damage.
|
|
|
|